infeasible, then a design, equipment, work practice, operational standard, or combination
thereof, may be prescribed instead to satisfy the requirement for the application of best
available control technology. The standard shall, to the degree possible, set forth the
emissions reduction achievable by implementation of the design, equipment, work
practice, or operation, and shall provide for compliance by means which achieve equivalent
results.
(g) “Building, structure, facility, or installation” means all of the pollutant-emitting
activities which belong to the same industrial grouping, are located on 1 or more contiguous
or adjacent properties, and are under the control of the same person, or persons under
common control, except the activities of any vessel. Pollutant-emitting activities are part
of the same industrial grouping if they have the same 2-digit major group code associated
with their primary activity. Major group codes and primary activities are described in the
standard industrial classification manual, 2017.
(h) “Clean coal technology” means any technology, including technologies applied at the
pre-combustion, combustion, or post-combustion stage, at a new or existing facility which
will achieve significant reductions in air emissions of sulfur dioxide or oxides of nitrogen
associated with the utilization of coal in the generation of electricity, or process steam
which was not in widespread use as of November 15, 1990.
(i) “Clean coal technology demonstration project” means a project using funds
appropriated under the heading "Department of Energy -- Clean Coal Technology," up to
a total amount of $2,500,000,000 for commercial demonstration of clean coal technology,
or similar projects funded through appropriations for the United States Environmental
Protection Agency. The federal contribution for a qualifying project shall be at least 20%
of the total cost of the demonstration project.
(j) [Reserved]
(k) “Commence,” as applied to construction of a major stationary source or major
modification, means that the owner or operator has all necessary preconstruction approvals
or permits and has done either of the following:
(i) Begun, or caused to begin, a continuous program of actual on-site construction of the
source, to be completed within a reasonable time.
(ii) Entered into binding agreements or contractual obligations, which cannot be
canceled or modified without substantial loss to the owner or operator, to undertake a
program of actual construction of the source to be completed within a reasonable time.
(l) “Complete” means, in reference to an application for a permit, that the application
contains all the information necessary for processing the application. Designating an
application complete for purposes of permit processing does not preclude the department
from requesting or accepting additional information.
(m) “Construction” means any physical change or change in the method of operation,
including fabrication, erection, installation, demolition, or modification of an emissions
unit, that would result in a change in emissions.
(n) “Continuous emissions monitoring system” or “CEMS” means all of the equipment
that may be required to meet the data acquisition and availability requirements of these
rules, to sample, condition if applicable, analyze, and provide a record of emissions on a
continuous basis.
Page 4
Courtesy of Michigan Administrative Rules