DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS  
PUBLIC SERVICE COMMISSION  
GAS SAFETY  
(By authority conferred on the public service commission by section 2 of 1969 PA  
165, MCL 483.152, and section 231 of the Executive organization act of 1965, 1965 PA  
380, MCL 16.331, and Executive Reorganization Order Nos. 1996-2, 2003-1, 2008-4,  
2011-4, and 2015-3, MCL 445.2001, 445.2011, 445.2025, 445.2030, and 460.21)  
PART 1. GENERAL PROVISIONS  
R 460.20101 Applicability of rules.  
Rule 101. (1) These rules apply to the design, fabrication, installation, inspection,  
testing, and safety aspects of the operation and maintenance of gas pipeline facilities used  
in the transportation of gas.  
(2) These rules do not apply to either of the following:  
(a) The onshore gathering of gas under either of the following conditions:  
(i) Through a pipeline that operates at less than 0 psig.  
(ii) Through a pipeline that is not a regulated onshore gathering line as determined  
by 49 C.F.R. § 192.8.  
(b) Any pipeline system that transports only petroleum gas or petroleum gas and air  
mixtures under either of the following circumstances:  
(i) The pipeline has fewer than 10 customers and no portion of the system is located  
in a public place.  
(ii) The pipeline has only 1 customer.  
(3) The work performed within the scope of these rules shall meet or exceed all of  
the safety standards in these rules.  
History: 1998-2000 AACS; 2009 AACS; 2014 AACS.  
R 460.20102 Definitions.  
Rule 102. As used in these rules:  
(a) "Commission" means the Michigan public service commission.  
(b) "Corrosion" means the destruction or deterioration of a material, usually a  
metal, by an electrochemical process, due to a reaction with the material's environment.  
(c) "Customer" means a person or company who purchases gas from a  
distributor for the person's or company's own use or for the use of a tenant, or both.  
(d) "Hoop stress" means the stress in a pipe wall which acts  
circumferentially in a plane perpendicular to the longitudinal axis of the pipe and which  
is produced by the pressure of the fluid in the pipe.  
(e) "Leak" means the unintentional escape of gas from a pipeline facility or a  
customer's facility.  
Page 1  
(f) "Leakage survey" means a systematic inspection that is made to locate leaks in a  
gas pipeline.  
(g) "Pressure" means gauge pressure, unless otherwise stated, expressed in pounds  
per square inch above atmospheric pressure and is abbreviated "psig."  
(h) "Sour gas" means gas containing a concentration of hydrogen sulfide (H2S)  
greater than or equal to 300 parts per million (ppm.).  
(i) "System" means all pipeline facilities used by a particular operator in the  
transportation of gas, including all of the following:  
(A) Line pipe.  
(B) Valves.  
(C) Other appurtenances connected to line pipe.  
(D) Compressor units.  
(E) Fabricated assemblies associated with compressor units.  
(F) Metering.  
(G) Customers' meters.  
(H) Delivery stations.  
(I) Fabricated assemblies in metering and delivery stations.  
(j) "Vault" means an underground structure that may be entered and that is designed  
to contain piping and piping components, such as valves and pressure regulators. The  
terms "vault"and "pit" are used interchangeably in these rules.  
History: 1998-2000 AACS.  
R 460.20103 Adoption of documents by reference generally.  
Rule 103. (1) Any documents or parts of documents adopted by reference in these  
rules are a part of these rules as though set out in full. When only a portion of a  
document is referenced, the remainder is not adopted in these rules.  
(2) Copies of all adopted documents are available at the addresses provided in R  
460.20602.  
(3) The full titles for the publications adopted by reference in these  
rules are provided in R 460.20603 to R 460.20606. Numbers in parentheses  
indicate applicable editions of the publications. Earlier editions of documents listed  
or editions of documents formerly listed in the Michigan gas safety code (R 460.14001 to  
R 460.14999) or these rules may be used for materials and components manufactured,  
designed, or installed in accordance with the earlier editions or earlier documents at the  
time they were listed. The user shall refer to the appropriate previous version of the  
Michigan gas safety code or these rules for a listing of the earlier listed editions or  
documents.  
(4) Standards and specifications cited in R 460.20603 to R 460.20606 may be  
supplemented by specific requirements elsewhere in these rules. Users of these rules are  
advised against attempting direct application of any of these standards without carefully  
observing the rule's reference to that standard.  
History: 1998-2000 AACS.  
Page 2  
R 460.20104 Rescission.  
Rule 104. R 460.14001 to R 460.14999 of the Michigan Administrative Code, noted  
on page 1027 of the 1997 Annual Supplement to the 1979 Michigan Administrative Code  
and appearing on pages 630 to 642 of the 1986 Annual Supplement to the Code, pages  
900 to 917, 919 to 921, and 923 to 925 of the 1991 Annual Supplement to the Code, and  
pages 1175 to 1199 of the 1995 Annual Supplement to the Code, are rescinded.  
History: 1998-2000 AACS; 2022 AACS.  
PART 2. SAFETY STANDARDS AND TESTING REQUIREMENTS  
R 460.20201 Pipeline safety standards; adoption by reference.  
Rule 201(1) Except for 49 C.F.R. §192.1, an operator shall ensure that a gas  
pipeline is in compliance with all of the minimum safety standards contained in 49 C.F.R.  
part 192 entitled “Transportation of Natural and Other Gas by Pipeline: Minimum  
Federal Safety Standards,” which are adopted by reference in R 460.20606.  
(2) An operator shall ensure that a pipeline that is subject to the standards specified  
in subrule (1) of this rule is also in compliance with all of the additional safety standards  
contained in R 460.20301 to R 460.20338.  
(3) In addition to the requirements imposed by subrules (1) and (2) of this rule, an  
operator shall ensure that a pipeline which transports sour gas is also in compliance with  
the additional safety standards contained in R 460.20401 to R 460.20431.  
History: 1998-2000 AACS; 2003 AACS; 2019 AACS.  
R 460.20202 Drug and alcohol testing requirements.  
Rule 202. (1) An operator shall meet the drug and alcohol testing  
requirements in 49 C.F.R. part 199 entitled "Drug and Alcohol Testing," which is  
adopted by reference in R 460.20606.  
(2) An operator shall conduct the drug and alcohol testing required by subrule (1)  
of this rule according to the requirements of 49 C.F.R. part 199 and the procedures  
prescribed in 49 C.F.R. part 40 entitled "Procedures for Transportation Workplace Drug  
and Alcohol Testing Programs," which is adopted by reference in R 460.20606.  
(3) Subrule (1) of this rule applies only to operators who operate facilities  
subject to the natural gas pipeline safety act of 1968, 49 U.S.C.§60101 et seq., as  
amended.  
History: 1998-2000 AACS.  
PART 3. ADDITIONAL MINIMUM SAFETY STANDARDS  
R 460.20301 Scope.  
Page 3  
Rule 301. (1) The rules contained in this part are additional requirements  
for the design, fabrication, installation, inspection, testing, and safety aspects of the  
operation and maintenance of gas pipeline facilities operated within the state of  
Michigan.  
(2) Operators of pipeline facilities used in the transportation of gas that are under  
the jurisdiction of the commission shall meet all of the requirements of 49 C.F.R.  
§192, which is adopted by reference in R 460.20606, and all of the additional  
requirements in this part.  
History: 1998-2000 AACS.  
R 460.20302 Compressor station piping.  
Rule 302. (1) An operator shall install and test gas piping, other than instrument,  
control, and sample piping, in accordance with these rules.  
(2) An operator shall identify all emergency valves and controls by signs. An  
operator shall identify important gas pressure piping by signs or color coding to indicate  
its function.  
(3) An operator shall ensure that fuel gas lines within  
conform to both of the following provisions:  
a
compressor station  
(a) Are provided with master shutoff valves located outside of a building.  
(b) Are equipped with pressure limiting devices to prevent the maximum  
allowable operating pressure from being exceeded by more than 10%.  
(4) An operator shall equip the air piping within a compressor station that is part  
of an air starter with a check valve in the starting air line near each engine to prevent  
backflow from the engine into the air piping system. An operator shall also place a  
similar check valve in the main air line on the immediate outlet side of the air tank or  
tanks. An operator shall install equipment for cooling the air and removing the  
moisture and entrained oil between the starting air compressor and the air storage tank.  
History: 1998-2000 AACS; 2009 AACS.  
R 460.20303 Vault and pit sealing, venting, and ventilation.  
Rule 303. In addition to the requirements contained in 49 C.F.R.§192.187(a)(3),  
which is adopted by reference in R 460.20606, an operator shall ensure that the outside  
end of the ventilation ducts of an underground vault or closed top pit is equipped with a  
suitable weatherproof fitting or vent head designed to prevent foreign matter from  
entering or obstructing the duct.  
History: 1998-2000 AACS.  
R 460.20304 Welding procedures.  
Rule 304. In addition to the requirements contained in 49 C.F.R. §192.225, which is  
adopted by reference in R 460.20606, an operator shall ensure that a welding procedure  
meets all of the following requirements:  
Page 4  
(a) Is qualified under section IX of the ASME boiler and pressure vessel code,  
which is adopted  
by reference in R 460.20604, or section 5, section 12, or appendix A of API standard  
1104, which is adopted by reference in R 460.20603, whichever is appropriate to the  
function of the weld.  
(b) Is qualified under appendix B of API standard 1104, which is adopted by  
reference in R 460.20603 for pipelines operating at greater than 60 psig.  
(c) A copy of the welding procedure being followed is on the jobsite when welding  
is performed.  
History: 1998-2000 AACS; 2009 AACS; 2014 AACS; 2019 AACS.  
Editor's Note: An obvious error in R 460.20304 was corrected at the request of the promulgating  
agency, pursuant to Section 56 of 1969 PA 306, as amended by 2000 PA 262, MCL 24.256. The rule  
containing the error was published in Michigan Register, 2019 MR 1. The memorandum requesting the  
correction was published in Michigan Register, 2019 MR 1.  
R 460.20305 Welder qualification records.  
Rule 305. An operator shall establish and maintain a record of all qualified  
welders that indicates the date and results of tests. The record shall specifically include  
the welding procedure for which each welder has qualified. An operator shall make the  
record available for inspection at each jobsite.  
History: 1998-2000 AACS.  
R 460.20306 Nondestructive testing.  
Rule 306. (1) In addition to the nondestructive testing required under 49 C.F.R.  
§192.243(d), which is adopted by reference in R 460.20606, an operator shall also ensure  
that 100% of each day’s field butt welds are nondestructively tested over their entire  
circumferences in the following locations:  
(a) Regulating stations.  
(b) Measuring stations.  
(c) Compressor stations.  
(2) If it is not practical to test 100% of each day's field butt welds as required by  
subrule (1) of this rule, then an operator shall nondestructively test at least 90% of each  
day's field butt welds selected at random at the locations specified in subrule (1) of this  
rule.  
History: 1998-2000 AACS; 2010 AACS; 2019 AACS.  
R 460.20307 Welding preheating.  
Rule 307. In addition to the requirements contained in 49 C.F.R.§192.235, which is  
adopted by reference in R 460.20606, if preheating is required, then an operator shall  
monitor the preheat temperature to ensure that the required preheat temperature is  
reached before beginning, and is maintained during, the welding operation.  
Page 5  
History: 1998-2000 AACS.  
R 460.20308 Customer meters and regulators; location.  
Rule 308. The requirements contained in 49 CFR 192.353, which is adopted by  
reference in R 460.20606, are superseded by all of the following provisions:  
(a) An operator shall install a customer’s meter and regulator outside the building,  
unless any of the following apply:  
(i) The distribution system operates at 10 psig or less and an outside meter set  
assembly is not practical.  
(ii) The building is a commercial building, industrial building, or apartment  
building and an outside meter set assembly is not practical.  
(iii) The building is a row-type house or house where the proximity of adjoining  
buildings makes outside meter set assemblies impractical.  
(b) A service line excluded under subdivision (a) of this rule must include an  
outside above grade riser, if practical.  
(c) If an outside meter set assembly or an outside above grade riser is installed, then  
the  
above grade piping must be designed to prevent an external force applied to the  
service line from being transferred to and damaging the inside piping.  
(d) An operator shall install a meter and service regulator, whether inside or outside  
of a building, in a readily accessible location and shall protect the meter and regulator  
from corrosion and other damage, including but not limited to, vehicular damage if  
installed outside a building. An operator shall not install a meter in a bedroom, closet,  
bathroom, under a combustible stairway, or in an unventilated or inaccessible place.  
(e) An operator shall ensure that a service regulator installed inside a building is  
located as near as practical to the point of service line entrance.  
(f) An operator shall ensure that a meter installed inside a building is located in a  
ventilated place not less than 3 feet from a source of ignition or heat that might damage  
the meter.  
(g) An operator shall ensure that the upstream regulator in a series is located outside  
of a building unless it is located in a separate metering or regulating building.  
History: 1998-2000 AACS; 2019 AACS; 2022 AACS.  
R 460.20309 Service lines; valve location.  
Rule 309. (1) In addition to the requirements contained in 49 C.F.R.§192.365,  
which is adopted by reference in R 460.20606, an operator shall ensure that service  
lines are equipped with a valve located on the service line outside the building if any of  
the following provisions apply:  
(a) The service line operates at a pressure of more than 10 psig.  
(b) The service line is 2 inches or larger in diameter.  
(c) The service line supplies any of the following:  
(i) A hospital.  
(ii) A church.  
Page 6  
(iii) A theater.  
(iv) A school.  
(v) A building of public assemblage similar to the buildings listed in paragraphs  
(i) to (iv) of this subdivision.  
(vi) A commercial or industrial building.  
(vii) A dwelling that houses more than 4 families.  
(2) An operator shall ensure that an outside valve required by subrule (1) of this  
rule is located aboveground in an accessible place, if feasible.If an aboveground location  
is not feasible, then the operator shall ensure that a curb valve or other remote valve is  
installed.  
(3) If a curb valve is installed, then the operator shall establish a planned  
procedure which permits accurately locating the service line valve within a reasonable  
period of time when the service line valve is not plainly visible at the surface of the  
ground during all periods of the year.  
History: 1998-2000 AACS; 2009 AACS.  
R 460.20310 Galvanized or aluminum pipe prohibited for direct burial or  
submerged use.  
Rule 310. (1) In addition to the requirements contained in 49 C.F.R.§192.461,  
which is adopted by reference in R 460.20606, an operator shall not utilize galvanized  
pipe for direct burial or submerged use.  
(2) The requirements contained in 49 C.F.R. §192.455(e), which is adopted by  
reference in R 460.20606, are superseded by the requirement that an operator shall not  
utilize aluminum pipe for direct burial or submerged use.  
History: 1998-2000 AACS; 2019 AACS.  
R 460.20311 Test Requirements for pipelines operating below 100 psig.  
Rule 311. The requirements contained in 49 CFR 192.509(b), which is adopted by  
reference in R 460.20606, are superseded by both of the following provisions:  
(a) An operator shall ensure that all mains are to be pressured tested to at least 90  
psig or 1 ½ times the proposed maximum allowable operating pressure, whichever is  
greater.  
(b) An operator shall ensure that the test pressure is maintained at or above the test  
pressure requirement for the pipeline being tested for not less than 1 hour. However, the  
operator shall test a relatively short segment for not less than 30 minutes.  
History: 1998-2000 AACS; 2022 AACS.  
R 460.20312 Test requirements; service lines other than plastic.  
Rule 312. The requirements contained in 49 C.F.R.§192.511(b) and (c), which are  
adopted by reference in R 460.20606 are superseded by the requirement that an operator  
shall test all service lines, other than plastic service lines, to a minimum pressure of 90  
Page 7  
psig, but not less than 150% of the maximum allowable operating pressure, for not less  
than 10 minutes. Each segment of a steel service line stressed to 20% or more of  
specified minimum yield strength must still be tested in accordance with 49 C.F.R. §  
192.507, which is adopted by reference in R 460.20606.  
History: 1998-2000 AACS; 2019 AACS.  
Editor's Note: An obvious error in R 460.20312 was corrected at the request of the promulgating  
agency, pursuant to Section 56 of 1969 PA 306, as amended by 2000 PA 262, MCL 24.256. The rule  
containing the error was published in Michigan Register, 2019 MR 1. The memorandum requesting the  
correction was published in Michigan Register, 2019 MR 1.  
R 460.20313 Minimum test duration; plastic pipelines.  
Rule 313. In addition to the requirements contained in 49 C.F.R.§192.513, which is  
adopted by reference in R 460.20606, an operator shall test plastic pipelines according to  
all the following:  
(a) Except for plastic service lines, the test must be maintained at or above the  
pressure requirement for not less than one hour. However, an operator may test a  
relatively short segment for not less than 30 minutes.  
(b) All plastic service lines must be pressure tested for not less than 10 minutes.  
History: 1998-2000 AACS; 2019 AACS.  
R 460.20314 Test records.  
Rule 314. In addition to the requirements contained in 49 C.F.R.§192.517(a), which  
is adopted by reference in R 460.20606, an operator shall retain the following test record  
information:  
(a) The proposed maximum allowable operating pressure of the pipeline.  
(b) Except for distribution facilities, the existing class location of the area in which  
the pipeline will be installed.  
(c) The date the test was performed.  
History: 1998-2000 AACS; 2019 AACS.  
R 460.20315 Leaks occurring during uprating; repairs and monitoring required.  
Rule 315. (1) In addition to the requirements contained in 49 C.F.R. §192.553,  
which is adopted by reference in R 460.20606, if the new and higher maximum allowable  
operating pressure will be more than 10 psig, then an operator shall expose and repair and  
monitor a leak that is detected during the uprating operation.  
(2) An operator shall file a complete copy of the written plan described in 49 C.F.R.  
§192.553(c), which is adopted by reference in R 460.20606, with the commission not less  
than 30 calendar days before commencement of a project.  
History: 1998-2000 AACS; 2014 AACS.  
Page 8  
R 460.20316 Leakage survey and repair requirement before uprating.  
Rule 316. (1) In addition to the requirements contained in 49 C.F.R.§192.555(b)(2),  
which is adopted by reference in R 460.20606, an operator shall conduct a leakage survey  
and repair all leaks found before the operator begins uprating any segment of a steel  
pipeline to an operating pressure that will produce a hoop stress of 30% or more of the  
specified minimum yield strength for the pipeline.  
(2) The provisions contained in 49 C.F.R. §192.557(b)(2), which is adopted by  
reference in R 460.20606, are superseded by the requirement that before an operator  
begins uprating any segment of a steel pipeline to an operating pressure that will produce  
a hoop stress of less than 30% of the specified minimum yield strength, a leakage survey  
must be conducted and all leaks found shall be repaired.  
History: 1998-2000 AACS; 2019 AACS.  
Editor's Note: An obvious error in R 460.20316 was corrected at the request of the promulgating  
agency, pursuant to Section 56 of 1969 PA 306, as amended by 2000 PA 262, MCL 24.256. The rule  
containing the error was published in Michigan Register, 2019 MR 1. The memorandum requesting the  
correction was published in Michigan Register, 2019 MR 1.  
R 460.20317 Rescinded.  
History: 1998-2000 AACS; 2019 AACS.  
Editor's Note: An obvious error in R 460.20316 was corrected at the request of the promulgating  
agency, pursuant to Section 56 of 1969 PA 306, as amended by 2000 PA 262, MCL 24.256. The rule  
containing the error was published in Michigan Register, 2019 MR 1. The memorandum requesting the  
correction was published in Michigan Register, 2019 MR 1.  
R 460.20318 Gas leak investigation; establishment of service; customer leak  
complaint records.  
Rule 318. (1) An operator shall conduct an investigation of every gas leak report  
received as soon as possible. If the investigation reveals a hazardous situation, then the  
operator shall take immediate action to evacuate, repair, or isolate the facilities involved  
to reduce any danger to the public.  
(2) A distribution utility shall not establish gas service to an applicant until the  
utility has made a leakage test, using gas at utilization pressure, to ensure that the  
applicant's fuel line is gastight and has made a determination that gas odor is detectible,  
where applicable. If fuel lines are not present upon completion of meter installation, the  
operator shall comply with all of the following:  
(a) A valve shall be installed on the outlet piping of the meter. This valve shall be  
in the closed position.  
(b) The valve shall be tagged with contact information of the distribution utility and  
notice that the fuel line installation must comply with applicable fuel piping codes.  
(c) A mechanical device or fitting that will prevent the flow of gas shall be installed  
at the outlet piping.  
Page 9  
(3) An operator shall keep records of all customer leak complaints and the  
disposition of the complaints.  
History: 1998-2000 AACS; 2014 AACS.  
R 460.20319 Filing of operation and maintenance manual with commission staff  
required.  
Rule 319. In addition to the requirements contained in 49 C.F.R.§192.605, which is  
adopted by reference in R 460.20606, an operator shall file the operation and  
maintenance manual required by 49 C.F.R. §192.605 with the commission staff in paper  
or electronic form. The operation and maintenance manual must include procedures that  
address both the federal rules and the rules contained in the Michigan gas safety  
standards. An operator shall file a change in the operation and maintenance manual with  
the commission staff within 90 calendar days after the change is made. An operator shall  
identify the specific changes.  
History: 1998-2000 AACS; 2014 AACS; 2019 AACS.  
R 460.20320 Rescinded.  
History: 1998-2000 AACS; 2009 AACS.  
R 460.20321 Rescinded.  
History: 1998-2000 AACS; 2009 AACS.  
R 460.20322 Maximum allowable operating pressure of pipeline containing cast-  
iron pipe.  
Rule 322. The requirement contained in 49 CFR 192.621(a)(3), which is adopted by  
reference in R 460.20606, is superseded by the requirement that a person shall not  
operate any segment of a pipeline containing cast-iron pipe that has unreinforced bell and  
spigot joints at a pressure of more than 10 psig.  
History: 1998-2000 AACS; 2022 AACS.  
R 460.20323 Odorization of gas; records maintenance.  
Rule 323. In addition to the requirements contained in 49 C.F.R.§192.625, which is  
adopted by reference in R 460.20606, an operator shall establish and maintain adequate  
records to establish compliance with the requirements of 49 C.F.R. §192.625,  
including the quantity of odorant used per million cubic feet of gas and sampling to  
determine the effectiveness of odorization.  
Page 10  
History: 1998-2000 AACS.  
R 460.20324 Fenced areas; alternate means of exit.  
Rule 324. An operator shall ensure that a fence which may hamper or prevent  
the escape of persons from the vicinity of a meter or regulator station in an  
emergency has an alternate means of exit, such as a second gate, exit ladder, or  
platform.  
History: 1998-2000 AACS.  
R 460.20325 Transmission line patrolling.  
Rule 325. In addition to the requirements contained in 49 C.F.R.§192.705, which is  
adopted by reference in R 460.20606, at intervals of not more than 6 weeks, but not less  
than 12 times each calendar year, an operator shall patrol all transmission lines that are  
operating at 40% or more of specified minimum yield strength to observe surface  
conditions on, and adjacent to, the transmission line right-of-way for indications of  
leaks, construction activity, and other factors affecting safety and operation.  
History: 1998-2000 AACS.  
R 460.20326 Transmission lines; permanent field repair of leaks.  
Rule 326. (1) The requirements contained in 49 C.F.R. §192.717(b)(3), which is  
adopted by reference in R 460.20606, are superseded by the requirement that an operator  
shall not repair a transmission pipeline through the use of a welded patch.  
(2) The requirements of 49 C.F.R. § 192.711(c) are superseded by the requirement  
that an operator shall not repair a leak through the use of a welded patch.  
History: 1998-2000 AACS; 2009 AACS; 2019 AACS.  
R 460.20327 Distribution system; leakage surveys and procedures.  
Rule 327. In addition to the requirements contained in 49 C.F.R. §192.723, which is  
adopted by reference in R 460.20606, all of the following requirements apply:  
(a) A gas leak located by a survey that, due to its location or relative magnitude,  
constitutes a hazard or potential hazard to the public or to buildings shall receive  
immediate corrective action. Immediate corrective action shall consist of an immediate  
effort to protect life and property and continuous remedial action thereafter until the  
condition is no longer hazardous.  
(b) An operator shall schedule a gas leak which does not constitute an immediate  
hazard to the public or to buildings, but which requires scheduled repair within the  
operator's maintenance manual, for repair within 1 year.  
(c) An operator shall ensure that a gas leak which is located by a survey, other than  
a leak covered by subdivision (a) or (b) of this rule, is subjected to regular surveillance at  
intervals not exceeding 15 months, but at least once each calendar year.  
Page 11  
History: 1998-2000 AACS; 2014 AACS.  
R 460.20328 Pressure-limiting and pressure-regulating stations; inspection and  
testing.  
Rule 328. In addition to the requirements contained in 49 C.F.R.§192.739, which is  
adopted by reference in R 460.20606, an operator shall tag a pressure-limiting or  
pressure-relief device installed to provide overpressure protection to a transmission  
line or distribution main to indicate the maximum allowable operating pressure of the  
facilities being protected and the set pressure or shall make  
information available at each location.  
a
record of the  
History: 1998-2000 AACS.  
R 460.20329 Valve maintenance; distribution systems.  
Rule 329. In addition to the requirements contained in 49 CFR 192.747, which is  
adopted by reference in R 460.20606, an operator shall partially operate a valve that may  
be necessary for the safe operation of a distribution system, other than plastic valves, at  
intervals of not more than 15 months, but at least each calendar year.  
History: 1998-2000 AACS; 2022 AACS.  
R 460.20330 Prevention of accidental ignition.  
Rule 330. In addition to the requirements contained in 49 C.F.R.§192.751, which is  
adopted by reference in R 460.20606, before welding in or around a vault, pit, or other  
structure or area containing gas facilities, an operator shall make a thorough check to  
determine the possible presence of a combustible gas mixture. Welding shall begin only  
when safe conditions are indicated.  
History: 1998-2000 AACS.  
R 460.20331 Caulked bell and spigot joints.  
Rule 331. The requirements contained in 49 C.F.R.§192.753(a), which is adopted  
by reference in R 460.20606, are superseded by the following:  
(a) An operator shall seal a cast-iron, caulked bell and spigot joint subject to  
pressures of more than 10 psig with either of the following:  
(i) A mechanical leak clamp.  
(ii) A material or device that has all of the following characteristics:  
(A) Does not reduce the flexibility of the joint.  
(B) Permanently bonds, either chemically or mechanically, or both, with the bell  
and spigot metal surfaces or adjacent pipe metal surfaces.  
(C) Seals and bonds in a manner that meets the strength, environmental, and  
chemical compatibility requirements of 49 C.F.R.§192.53 and 49 C.F.R. §192.143, which  
are adopted by reference in R 460.20606.  
Page 12  
History: 1998-2000 AACS; 2019 AACS.  
R 460.20332 Discontinuation of inactive service lines.  
Rule 332. (1) In addition to complying with the requirements contained in 49 C.F.R.  
§ 192.727, which is adopted by reference in R 460.20606, an operator shall, within 9  
months after a service line becomes inactive, discontinue gas service for any inactive  
service line with components located inside a structure pursuant to the methods specified  
in either of the following regulations:  
(i) In accordance with 49 C.F.R. § 192.727(d)(1) and (d)(2).  
(ii) In accordance with 49 C.F.R. § 192.727(d)(3) by physically disconnecting the  
service line outside the building.  
(2) As used in subrule (1) of this rule, “inactive service line” means a service line  
where there has been no customer of record for a continuous 24-month period and gas  
service to the premises has not been discontinued.  
History: 2014 AACS; 2019 AACS.  
R 460.20335 Master meter systems.  
Rule 335. (1) The definition of “master meter system” contained in 49 C.F.R.  
§191.3, which is adopted by reference in R 460.20606, is superseded by the following:  
(a) As used in these rules, “master meter system” means a distribution pipeline  
system that receives metered gas from an outside source and that is used for distributing  
gas within a definable area, including but not limited to, a mobile home park, vacation  
rental housing complex, apartment complex, college campus, or prison. The master  
meter system supplies the ultimate consumer of the gas whether the gas is purchased or  
supplied at no cost.  
(b) As used in this rule, “distribution pipeline system” means a system of main and  
service lines including all parts of those physical facilities through which gas moves in  
transportation, including but not limited to, pipe, valves, and other appurtenance attached  
to pipe, metering stations, regulator stations, delivery stations, holders, and fabricated  
assemblies. The distribution pipeline system ends at the outlet of the sub-meter, the  
outlet of the service regulator, or the building wall, whichever is furthest downstream.  
(c) As used in this rule, “ultimate consumer” means a third-party end-user  
occupying an area containing distribution piping from the distribution pipeline system  
who routinely consumes gas from the system.  
(d) As used in this rule, “sub-meter” means 1 of 2 or more meters for measuring  
different sections of gas supply that is located downstream from a master meter.  
(2) An operator shall not supply gas to any new master meter system established on  
or after January 1, 2019 unless the commission has provided a waiver.  
(3) The design, construction, inspection, and testing of additions to existing master  
meter systems are the responsibility of the operator with the direct costs paid by the  
owner, unless the commission has provided a waiver.  
(4) Unless the commission has provided a waiver, for master meter systems that  
were established before January 1, 2019, an operator shall make efforts to negotiate an  
Page 13  
operations and maintenance agreement with the master meter system owner that ensures  
compliance with all applicable requirements of the gas safety standards for that system.  
The direct cost to the operator for services performed under this agreement, including an  
appropriate administrative overhead, may be charged to the owner of the master meter  
system. The monthly charge per service line must not exceed the residential meter  
charge or customer charge included in the operator’s tariffs on January 1, 2018. An  
operator shall apply for any necessary waivers under this subrule by January 1, 2020.  
(5) Beginning March 15, 2019, all operators shall provide an annual report to the  
commission describing the location, type of facility served, number of services at each  
known master meter system in service at the end of the previous calendar year, and the  
names and contact information for all known master meter system owners with whom the  
operator is unable to execute an operations and maintenance contract.  
History: 2019 AACS.  
R 460.20338 Farm taps.  
Rule 338. (1) As used in this rule, “farm tap” means a distribution line directly  
connected to a production, gathering, or transmission pipeline not operated as part of a  
distribution system, or to a natural gas producing well, compressor station, or gas  
processing facility that delivers gas to a landowner or occupant other than the operator.  
(2) Effective January 1, 2019, an operator shall not construct any new farm taps  
unless all of the following apply:  
(a) The operator is a public utility as defined in section 1 of 1972 PA 299, MCL  
460.111.  
(b) The farm tap complies with all of the requirements of the gas safety standards.  
(c) The gas supplied meets the requirements for gas quality set forth in part 8 of the  
technical standards for gas service, R 460.2381 and R 460.2382.  
(3) This rule does not apply to domestic wells. As used in this rule, “domestic well”  
means a well that produces gas and that is owned by the owner of the surface estate on  
which the well is located and that is used only to provide gas for the owner’s domestic  
use.  
(4) Beginning March 15, 2019, all operators supplying gas to 1 or more farm taps  
shall provide an annual report on the status of farm taps connected to the operator’s  
facilities. The report must include the location of each farm tap connection, safety  
equipment installed on each connection, and the source of gas supply. This reporting  
requirement does not apply to farm taps connected to transmission pipelines operated by  
distribution utilities.  
History: 2019 AACS.  
Editor's Note: An obvious error in R 460.20338 was corrected at the request of the promulgating  
agency, pursuant to Section 56 of 1969 PA 306, as amended by 2000 PA 262, MCL 24.256. The rule  
containing the error was published in Michigan Register, 2019 MR 1. The memorandum requesting the  
correction was published in Michigan Register, 2019 MR 1.  
Page 14  
PART 4. SOUR GAS PIPELINES  
R 460.20401 Scope; conversion of existing pipeline to sour gas service.  
Rule 401. (1) The rules in this part are additional requirements for the design,  
fabrication, installation, inspection, testing, and safety aspects of the operation and  
maintenance of gas pipeline facilities used in the transportation of sour gas.  
(2) Operators of pipeline facilities used for the transportation of sour gas that  
are under the jurisdiction of the commission shall meet all of the requirements in parts  
2, 3, and 5 of these rules, all of the requirements in 49 C.F.R. Part 192, which is  
adopted by reference in R 460.20606, and all of the additional requirements in this  
part.  
(3) Existing pipeline facilities not designed and built for the transportation  
of sour gas shall not be converted for use in the transportation of sour gas  
without prior review and approval of the commission.  
History: 1998-2000 AACS; 2003 AACS.  
R 460.20402 Materials for pipe and components; requirements.  
Rule 402. In addition to the requirements in 49 CFR 192.55, which is adopted by  
reference in R 460.20606, metallic materials for pipe and other components used to  
transport sour gas must meet the requirements in the National Association of Corrosion  
Engineers international standard NACE MR0175/ISO 15156, which are adopted by  
reference in R 460.20605.  
History: 1998-2000 AACS; 2003 AACS; 2009 AACS; 2010 AACS; 2022 AACS.  
R 460.20403 Steel pipe; design formula.  
Rule 403. In addition to the requirements set forth in 49 C.F.R. §192.105 through  
§192.115, which are adopted by reference in R 460.20606, steel pipe designed for use in  
the transportation of sour gas shall use a design factor of 0.40.  
History: 1998-2000 AACS; 2003 AACS.  
R 460.20404 Purging of sour gas pipelines; plan; personnel.  
Rule 404. In addition to satisfying the requirements set forth in 49 C.F.R.  
§192.629, which is adopted by reference in R 460.20606, an operator of pipeline facilities  
used in the transportation of sour gas shall  
provisions:  
comply with both of the following  
(a) The purging of sour gas from a pipeline shall be accomplished by burning  
or by equivalent control of H2S.  
(b) All purging and blowing down of sour gas pipelines shall be done in  
accordance with a written plan. The plan shall include  
public and operator  
personnel safety and environmental protection considerations. Properly equipped  
Page 15  
personnel who are trained and familiar with the potential hazards of sour gas shall  
perform all purging and blowing down operations.  
History: 1998-2000 AACS; 2003 AACS.  
R 460.20405 Valves; qualification for sour gas.  
Rule 405. An operator shall ensure that valves that are used for sour gas service are  
qualified for sour gas service in accordance with the National Association of Corrosion  
Engineers international standard MR-175/ISO 15156, which is adopted by reference in R  
460.20605.  
History: 1998-2000 AACS; 2003 AACS; 2009 AACS; 2010 AACS; 2022 AACS.  
R 460.20406 Compressor station; emergency shutdown.  
Rule 406. In addition to the requirements  
set  
forth in 49  
C.F.R.§192.167(a)(2), which is adopted by reference in R 460.20606, if there is an  
emergency shutdown, all gas released from sour gas pipeline facilities shall be flared in a  
manner that minimizes the danger to the general public.  
History: 2003 AACS.  
R 460.20407 Sectionalizing block valves.  
Rule 407. In addition to the requirements in 49 C.F.R. §192.179, which is adopted  
by reference in R 460.20606, an operator of pipeline facilities used in the transportation  
of sour gas shall comply with all of the following requirements for any portion of the  
pipeline that contains more than 10 pounds of H2S per mile, with the weight calculated  
according to the formula:  
PxVxMxH  
W=9.318x10-8-------------------------, where:  
T
W=Weight of H2S in pounds per mile of pipe,  
P=Absolute pressure in pounds per square inch,  
V=Volume of one mile of pipe in cubic feet,  
M=Molecular weight of the gas in grams per mole,  
H= Quantity of H2S in the gas in parts per million,  
T=Temperature in degrees Rankine:  
(a) Sectionalizing block valves must be installed and located so that each point on  
the pipeline is within 3 miles of a sectionalizing block valve with a block valve located at  
each end of the pipeline.  
(b) A pipeline must incorporate block valve automation so that block valves will  
automatically close upon the registering of low pressure readings. The system must be  
Page 16  
designed to operate even in the event of a power failure or malfunction of electronic  
devices and must be designed to fail in a closed position.  
(c) A pipeline must incorporate a supervisory control and data acquisitions  
(SCADA) system that complies with all of the following provisions:  
(i) Is monitored by the operator to ensure appropriate response to emergencies.  
(ii) Is programmed to automatically close block valves based on operating data  
gathered at each metering site and at each automated block valve.  
(iii) Automatically closes the upstream and downstream sectionalizing block valves  
surrounding any sectionalizing block valve that is in an alarm condition.  
(iv) Allows the operator monitoring the SCADA system to close, but not open, any  
or all of the block valves and metering points.  
(d) H2S sensors must be located at all sectionalizing block valve sites. The sensors  
must provide a warning to the SCADA system at H2S levels of 10 ppm and shall close  
the block valve at H2S levels of 30 ppm.  
(e) Control valves must be installed at appropriate locations at well sites or laterals  
to automatically shut off the flow of gas into the pipeline in the event of a line break or  
over pressure conditions.  
History: 2003 AACS; 2009 AACS; 2010 AACS; 2019 AACS.  
R 460.20408 Qualification of welding procedures.  
Rule 408. In addition to the requirements 49 CFR 192.225, which is adopted by  
reference in R 460.20606, an operator of pipeline facilities used in the transportation of  
sour gas shall use welding procedures that conform to the welding provisions of the  
National Association of Corrosion Engineers international standard NACE MR0175/ISO  
15156, which is adopted by reference in R 460.20605.  
History: 2003 AACS; 2009 AACS; 2010 AACS; 2022 AACS.  
R 460.20409 Inspection and testing of welds.  
Rule 409. In addition to the requirements set forth in 49 C.F.R.§192.241(b), which  
is adopted by reference in R 460.20606, an operator of pipeline facilities used in the  
transportation of sour gas shall engage in nondestructive testing of 100% of all girth butt  
welds. Nondestructive testing of welds shall be performed by any process that clearly  
indicates all defects in the welds.  
History: 2003 AACS; 2019 AACS.  
R 460.20410 Threaded joints.  
Rule 410. In addition to the requirements set forth in 49 C.F.R.§192.273,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall not use threaded joints to join any sections or  
other components of a buried pipeline.  
Page 17  
History: 2003 AACS.  
R 460.20411 Repair of steel pipe.  
Rule 411. In addition to the requirements set forth in 49 C.F.R.§192.309,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall remove any imperfection or damage  
discovered during construction that impairs the serviceability of a length of steel pipe  
by cutting out the damaged portion of the pipe as a cylinder and replacing it with an  
undamaged piece of pipe which meets or exceeds the specifications of the original  
pipe.  
History: 2003 AACS.  
R 460.20412 Strength test requirements.  
Rule 412. In addition to the requirements set forth in 49 C.F.R.§192.505,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall pressure test in place all sour gas pipelines to not  
less than 2 times their maximum allowable operating pressure (MAOP) for not less than 8  
hours.  
History: 2003 AACS.  
R 460.20413 Underground clearances.  
Rule 413. In addition to the requirements set forth in 49 C.F.R.§192.325,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall, if practical, install the pipeline with not less  
than 48 inches of clearance from all other underground structures not associated with  
the pipeline. If this clearance cannot be practicably attained, the pipeline shall be  
protected from damage that might result due to its proximity to the other structure or  
structures.  
History: 2003 AACS.  
R 460.20414 Cover.  
Rule 414. In addition to the requirements set forth in 49 C.F.R.§192.327,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall comply with all of the following provisions:  
(a) Pipelines shall be buried, except where  
necessitate above ground construction.  
special conditions of usage  
(b) A buried pipeline shall be installed with a minimum cover of 48 inches.  
(c) When practical, a warning tape shall be installed not less than 12 inches  
directly above the pipeline, but not more than 36 inches below grade, for the purpose  
Page 18  
of warning excavators of the existence of the pipeline and the hazardous nature of  
sour gas.  
History: 2003 AACS.  
R 460.20415 Pipeline location.  
Rule 415. In addition to the requirements set forth in 49 C.F.R.§192.327,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall comply with both of the following provisions:  
(a) A pipeline shall be routed to avoid class 3 and 4 locations, if practical.  
(b) Use of road rights-of-way shall be avoided, if practical.  
History: 2003 AACS.  
R 460.20416 Internal corrosion control; generally.  
Rule 416. In addition to the requirements set forth in 49 C.F.R.§192.475,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas  
shall  
not transport by pipeline any gas  
containing H2S, unless the corrosive effect of the H2S has been investigated and steps  
have been taken to minimize internal corrosion for the pipeline facilities.  
History: 2003 AACS.  
R 460.20417 Internal corrosion control; monitoring.  
Rule 417. In addition to the requirements set forth in 49 C.F.R.§192.477,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall use coupons or other suitable means to determine  
the effectiveness of the steps taken to minimize internal corrosion. Initially, each coupon  
or other means of monitoring internal corrosion shall be checked 4 times each  
calendar year, but with intervals of not more than 3 1/2 months until a monitoring  
schedule can be developed that will adequately identify internal corrosion. The  
monitoring schedule shall not exceed the schedule set forth in 49 C.F.R. §192.477.  
History: 2003 AACS.  
R 460.20418 Remedial measures.  
Rule 418. In addition to the requirements set forth in 49 C.F.R.§192.485,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall remove from service and replace every segment  
of a pipeline that has general corrosion resulting in a remaining wall thickness less  
than that required for the MAOP of the pipeline.  
History: 2003 AACS.  
Page 19  
R 460.20419 Sour gas pipeline operating and maintenance manual; contents.  
Rule 419. The manual required by 49 C.F.R. §192.605, which is adopted by  
reference in R 460.20606 and which shall be filed with the commission and updated as  
specified in R 460.20319, shall address all hazards inherent with the transportation of  
sour gas and shall contain plans and procedures to minimize the health risk to the  
operator's employees and the general public during normal operating conditions.  
History: 2003 AACS; 2014 AACS.  
R 460.20420 Safety procedures for abnormal operating conditions.  
Rule 420. The manual required by 49 C.F.R. §192.605, which is adopted by  
reference in R 460.20606 and which shall be filed with the commission and updated as  
specified in R 460.20319, shall also address the hazards inherent with the transportation  
of sour gas and shall include plans and procedures to minimize the health risk to the  
operator's employees and the general public during abnormal operating conditions.  
History: 2003 AACS; 2014 AACS.  
R 460.20421 Damage prevention program.  
Rule 421. In addition to the requirements set forth in 49 C.F.R.§192.614,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall comply with both of the following provisions:  
(a) When notified by the "One-Call" system or by other means of possible  
excavation activity in the pipeline right-of-way, the pipeline operator shall monitor  
the excavation activity using on-site personnel.  
(b) When responding to requests to mark the pipeline location, the operator  
shall notify the excavator of the hazards inherent in the release of sour gas.  
History: 2003 AACS.  
R 460.20422 Emergency procedures.  
Rule 422. The plan required by 49 C.F.R. §192.615, which is adopted by  
reference in R 460.20606, shall address the hazards inherent with the transportation  
of sour gas and shall include plans and procedures to minimize the health risk to the  
operator's employees and the general public in the event of an emergency.  
History: 2003 AACS.  
R 460.20423 Sour gas education programs.  
Rule 423. In addition to the requirements set forth in 49 C.F.R.§192.616,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
Page 20  
in the transportation of sour gas shall establish continuing education programs that  
enable the public, appropriate government organizations, and persons engaged  
in excavation-related activities to accomplish both of the following:  
(a) Recognize a sour gas pipeline emergency for the purpose of reporting it to the  
operator or other appropriate public officials.  
(b) Take appropriate action in the event of an unplanned release of sour gas.  
History: 2003 AACS.  
R 460.20424 Telephonic notice to the commission of sour gas leak.  
Rule 424.  
In addition to each of the reporting requirements set forth in R  
460.20503, an operator of pipeline facilities used in the transportation of sour gas shall,  
at the earliest practicable moment, but not more than 8 hours following the release of  
any quantity of sour gas that has the potential to harm the public, give telephonic  
notice to the commission staff of the release.  
History: 2003 AACS.  
R 460.20425 Sour gas pipeline patrolling.  
Rule 425. In addition to the requirements set forth in 49 C.F.R.§192.705,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall, at intervals of not more than 6 weeks, but not  
less than 12 times each calendar year, patrol all pipelines that are used in the  
transportation of sour gas.  
History: 2003 AACS; 2009 AACS.  
R 460.20426 Leakage surveys.  
Rule 426. In addition to the requirements set forth in 49 C.F.R.§192.706,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall conduct leak surveys of those pipeline facilities  
using leak detection equipment at intervals of not more than 7 1/2 months, but not less  
than 2 times each calendar year, for all areas falling within the class 1 and class 2  
location designations set forth in 49 C.F.R. §192.5, which is adopted by reference in R  
460.20606.  
History: 2003 AACS.  
R 460.20427 Line markers for sour gas pipelines.  
Rule 427. In addition to the requirements set forth in 49 C.F.R.§192.707,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall comply with both of the following provisions:  
Page 21  
(a) Line markers shall be placed and maintained as close as practical over a sour  
gas pipeline and shall clearly identify the pipeline as a carrier of sour gas.  
(b) Where practical, at least 1 line marker shall be visible from any location  
on the sour gas pipeline.  
History: 2003 AACS.  
R 460.20428 Prohibition on temporary repairs.  
Rule 428.  
(1)  
In addition to the requirements  
set  
forth  
in  
49  
C.F.R.§192.711, which is adopted by reference in R 460.20606, an operator of  
pipeline facilities used in the transportation of sour gas shall comply with all of the  
following provisions:  
(a) Temporary repairs are not allowed on pipeline facilities  
transportation of sour gas.  
used in the  
(b) Sour gas pipeline facilities in need of repair shall be removed from service  
until permanent repairs can be made.  
(2) This rule does not prohibit emergency repairs solely designed to protect  
the operator's employees and the public from a release of sour gas.  
History: 2003 AACS.  
R 460.20429 Permanent field repair of leaks.  
Rule 429. In addition to the requirements set forth in 49 C.F.R.§192.717,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall perform a permanent field repair of a leak by  
cutting out a cylindrical piece of pipe and replacing it with pipe of similar or greater  
design strength which meets the design criteria for facilities used in the transportation of  
sour gas.  
History: 2003 AACS.  
R 460.20430 Inspection of pressure limiting and pressure regulating stations.  
Rule 430. In addition to the requirements set forth in 49 C.F.R.§192.739,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
in the transportation of sour gas shall inspect all pressure limiting and pressure regulating  
devices at intervals of not more than 7 ½ months, but not less than twice each calendar  
year.  
History: 2003 AACS; 2009 AACS.  
R 460.20431 Valve maintenance; sour gas pipelines.  
Rule 431. In addition to the requirements set forth in 49 C.F.R.§192.745,  
which is adopted by reference in R 460.20606, an operator of pipeline facilities used  
Page 22  
in the transportation of sour gas shall inspect and partially operate each pipeline valve  
that might be required during an emergency at intervals of not more than 7 1/2  
months, but not less than twice each calendar year.  
History: 2003 AACS.  
PART 5. RECORDS AND REPORTS  
R 460.20501 Records.  
Rule 501. (1) An operator shall maintain the information generated by any  
recordkeeping requirement in these rules within the state at the operating headquarters  
office of each service area and shall make the information available to the commission  
and its staff for inspection and copying upon request.  
(2) An operator shall maintain all of the following additional records:  
(a) Maps and records showing the locations of pipelines and service lines, including  
lines that have been abandoned but not removed.  
(b) An up-to-date schematic drawing of station piping, which must be available at  
each aboveground pressure-regulating station containing buried station components.  
(3) In addition to the requirements contained in 49 CFR 192.603(b), which is  
adopted by reference in R 460.20606, an operator shall establish and maintain records,  
make reports, and record such information as may be reasonably required to demonstrate  
that the operator has acted or is acting in compliance with these rules and 49 CFR part  
192. The operator shall maintain these records and reports for the time periods  
prescribed in 49 CFR Part 192; for a minimum of 2 inspection cycles, if applicable; or for  
a minimum of 5 years, whichever is longer.  
(4) The specific record retention requirements for each rule or subrule, if required,  
are listed in Table 1, and are as follows:  
TABLE 1  
GAS SAFETY RECORD RETENTION SCHEDULES  
Rule  
Record  
Required Retention  
Additional  
Require Time  
Instructions  
d
PART 1: GENERAL PROVISIONS  
460.20101 (1)  
460.20101 (2)  
460.20101 (3)  
460.20102 (a)  
460.20102 (b)  
460.20102 (c)  
460.20102 (d)  
460.20102 (e)  
No  
No  
No  
No  
No  
No  
No  
No  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
None  
None  
None  
None  
None  
None  
None  
None  
Page 23  
460.20102 (f)  
460.20102 (g)  
460.20102 (h)  
460.20102 (i)  
460.20102 (j)  
460.20103 (1)  
460.20103 (2)  
460.20103 (3)  
460.20103 (4)  
460.20104  
No  
No  
No  
No  
No  
No  
No  
No  
No  
No  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
None  
None  
None  
None  
None  
None  
None  
None  
None  
None  
PART 2: SAFETY STANDARDS AND TESTING REQUIREMENTS  
460.20201 (1)  
460.20201 (2)  
460.20201 (3)  
460.20202 (1)  
460.20202 (2)  
460.20202 (3)  
No  
No  
No  
No  
No  
No  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
None  
None  
None  
None  
None  
None  
PART 3: ADDITIONAL MINIMUM SAFETY STANDARDS  
460.20301 (1)  
460.20301 (2)  
460.20302 (1)  
460.20302 (2)  
460.20302 (3)  
460.20302 (4)  
460.20303  
No  
No  
No  
No  
No  
No  
No  
Yes  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
5
None  
None  
None  
None  
None  
None  
None  
460.20304 (a)  
year minimum  
Consideration shall be given by  
(See  
instructions.)  
additionalthe operators to maintain these  
records for the life of the pipeline.  
460.20304 (b)  
Yes  
5
(See  
instructions.)  
N/A  
5
(See  
instructions.)  
year minimum  
Consideration shall be given by  
additionalthe operators to maintain these  
records for the life of the pipeline.  
None  
460.20304 (c)  
460.20305  
No  
Yes  
year minimum  
Operators shall maintain records  
additionaldemonstrating that welders welding  
pursuant to 49 CFR 192.229(a) have  
maintained their qualification back to  
their last destructive test, if longer  
than 5 years.  
460.20306 (1)  
460.20306 (2)  
460.20307  
460.20308 (a)  
460.20308 (b)  
Yes  
Yes  
No  
No  
No  
Life of pipeline  
Life of pipeline  
N/A  
N/A  
N/A  
None  
None  
None  
None  
None  
Page 24  
460.20308 (c)  
460.20308 (d)  
460.20308 (e)  
460.20308 (f)  
460.20308 (g)  
460.20309 (1)  
460.20309 (2)  
460.20309 (3)  
460.20310 (1)  
460.20310 (2)  
460.20311 (a)  
460.20311 (b)  
460.20311 (c)  
460.20311 (d)  
460.20312  
No  
No  
No  
No  
No  
No  
No  
No  
No  
No  
Yes  
Yes  
Yes  
Yes  
Yes  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
5 year minimum  
5 year minimum  
5 year minimum  
5 year minimum  
None  
None  
None  
None  
None  
None  
None  
None  
None  
None  
None  
None  
None  
None  
5
year minimum  
Except that each segment of a  
(See  
instructions.)  
additionalsteel service line stressed to 20% or  
more of specified minimum yield  
strength must be tested pursuant to  
49 CFR 192.507. This record must be  
retained for the life of the facility (49  
CFR 192.517(a)).  
460.20313 (a)  
460.20313 (b)  
460.20314 (a)  
460.20314 (b)  
460.20314 (c)  
460.20315 (1)  
460.20315 (2)  
460.20316 (1)  
460.20316 (2)  
460.20317  
Yes  
Yes  
Yes  
Yes  
Yes  
Yes  
Yes  
Yes  
Yes  
5 year minimum  
5 year minimum  
None  
None  
None  
None  
None  
None  
None  
None  
None  
Life of pipeline  
Life of pipeline  
Life of pipeline  
Life of pipeline  
Life of pipeline  
Life of pipeline  
Life of pipeline  
RESCINDED  
460.20318 (1)  
460.20318 (2)  
460.20318 (3)  
460.20319  
Yes  
Yes  
Yes  
No  
5 year minimum  
5 year minimum  
5 year minimum  
N/A (See additional  
None  
None  
None  
Consideration shall be given by  
the operators to maintain the most  
current submission of this record to  
the commission.  
instructions.)  
460.20320  
460.20321  
460.20322  
460.20323  
460.20324  
460.20325  
RESCINDED  
RESCINDED  
N/A  
5 year minimum  
N/A  
No  
Yes  
No  
None  
None  
None  
None  
Yes  
5 year minimum  
Page 25  
460.20326 (1)  
460.20326 (2)  
460.20327 (a)  
460.20327 (b)  
460.20327 (c)  
460.20328  
No  
No  
Yes  
Yes  
Yes  
No  
N/A  
N/A  
5 year minimum  
5 year minimum  
5 year minimum  
N/A  
None  
None  
None  
None  
None  
None  
460.20329  
460.20330  
Yes  
No  
5 year minimum  
N/A  
None  
None  
460.20331 (a)  
460.20332 (1)  
460.20332 (2)  
460.20335 (1)  
460.20335 (2)  
460.20335 (3)  
460.20335 (4)  
Yes  
Yes  
Yes  
No  
No  
No  
Life of pipeline  
5 year minimum  
5 year minimum  
N/A  
N/A  
N/A  
None  
None  
None  
None  
None  
None  
No  
N/A (See additional  
Consideration shall be given by  
the operators to maintain the most  
current submission of this record to  
the commission.  
instructions.)  
460.20335 (5)  
No  
N/A (See additional  
instructions.)  
Consideration shall be given by  
the operators to maintain the most  
current submission of this record to  
the commission.  
460.20338 (1)  
460.20338 (2)  
460.20338 (3)  
460.20338 (4)  
No  
No  
No  
No  
N/A  
N/A  
N/A  
None  
None  
None  
N/A (See additional  
Consideration shall be given by  
the operators to maintain the most  
current submission of this record to  
the commission.  
instructions.)  
PART 4: SOUR GAS PIPELINES  
460.20401 (1)  
460.20401 (2)  
460.20401 (3)  
460.20402  
460.20403  
460.20404 (a)  
No  
No  
Yes  
No  
Yes  
No  
N/A  
N/A  
Life of pipeline  
N/A  
Life of pipeline  
None  
None  
None  
None  
None  
N/A (See additional  
Consideration shall be given by  
the operators to maintain this record  
for the duration of the work requiring  
the procedure.  
instructions.)  
460.20404 (b)  
460.20405  
No  
No  
N/A (See additional  
instructions.)  
Consideration shall be given by  
the operators to maintain this record  
for the duration of the work requiring  
the procedure.  
N/A  
None  
Page 26  
460.20406  
No  
No  
No  
No  
No  
No  
Yes  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
5
None  
None  
None  
None  
None  
None  
460.20407 (a)  
460.20407 (b)  
460.20407 (c)  
460.20407 (d)  
460.20407 (e)  
460.20408  
year minimum  
Consideration shall be given by  
(See  
instructions.)  
additionalthe operators to maintain these  
records for the life of the pipeline.  
460.20409  
460.20410  
460.20411  
Yes  
No  
No  
Life of pipeline  
N/A  
N/A  
None  
None  
None  
460.20412  
460.20413  
Yes  
No  
Life of pipeline  
N/A  
None  
None  
460.20414 (a)  
460.20414 (b)  
460.20414 (c)  
460.20415 (a)  
460.20415 (b)  
460.20416  
No  
No  
No  
No  
N/A  
N/A  
N/A  
N/A  
N/A  
Life of pipeline  
5 year minimum  
None  
None  
None  
None  
None  
None  
None  
No  
Yes  
Yes  
Yes  
460.20417  
460.20418  
5
year minimum  
For transmission lines, repair  
(See  
additionalrecords must be maintained pursuant  
to 49 CFR 192.709.  
instructions.)  
instructions.)  
460.20419  
460.20420  
No  
No  
N/A (See additional  
Consideration shall be given by  
the operators to maintain the most  
current submission of this record to  
the commission.  
N/A (See additional  
instructions.)  
Consideration shall be given by  
the operators to maintain the most  
current submission of this record to  
the commission.  
460.20421 (a)  
460.20421 (b)  
460.20422  
Yes  
Yes  
No  
5 year minimum  
5 year minimum  
N/A (See additional  
None  
None  
Consideration shall be given by  
the operators to maintain the most  
current submission of this record to  
the commission.  
instructions.)  
460.20423 (a)  
460.20423 (b)  
No  
No  
N/A (See additional  
instructions.)  
Consideration shall be given by  
the operators to maintain the most  
current submission of this record to  
the commission.  
Consideration shall be given by  
the operators to maintain the most  
current submission of this record to  
N/A (See additional  
instructions.)  
Page 27  
the commission.  
460.20424  
460.20425  
460.20426  
460.20427 (a)  
460.20427 (b)  
460.20428 (1)  
Yes  
Yes  
Yes  
No  
No  
Yes  
5 year minimum  
5 year minimum  
5 year minimum  
N/A  
None  
None  
None  
None  
N/A  
None  
5
year minimum  
For transmission lines, repair  
(See  
instructions.)  
additionalrecords must be maintained pursuant  
to 49 CFR 192.709.  
460.20428 (2)  
460.20429  
Yes  
Yes  
5
(See  
instructions.)  
year minimum  
For transmission lines, repair  
additionalrecords must be maintained pursuant  
to 49 CFR 192.709.  
5
year minimum  
For transmission lines, repair  
additionalrecords must be maintained pursuant  
to 49 CFR 192.709.  
(See  
instructions.)  
5 year minimum  
5 year minimum  
460.20430  
460.20431  
Yes  
Yes  
None  
None  
PART 5: RECORDS AND REPORTS  
460.20501 (1)  
No  
N/A  
None  
460.20501 (2)(a)  
Yes  
Life of pipeline (See  
This record must be maintained  
additional instructions.) for pipelines that are abandoned and  
not removed.  
460.20501 (2)(b)  
460.20501 (3)  
No  
No  
N/A  
None  
N/A (See additional  
Requires an operator to maintain  
records as may be reasonably  
required to demonstrate compliance  
with these rules and 49 CFR part  
192. Records shall be maintained for  
a minimum of 2 inspection cycles or  
5 years, whichever is longer; or as  
otherwise directed on this table.  
Consideration shall be given by  
the operators to maintain this record  
for the duration of the project.  
Consideration shall be given by  
the operators to maintain this record  
for the duration of the project.  
Consideration shall be given by  
the operators to maintain this record  
for the duration of the project.  
Consideration shall be given by  
the operators to maintain this record  
for the duration of the project.  
None  
instructions)  
460.20502 (1)  
460.20502 (2)  
460.20502 (3)  
460.20502 (4)  
No  
No  
No  
No  
N/A (See additional  
instructions.)  
N/A (See additional  
instructions.)  
N/A (See additional  
instructions.)  
N/A (See additional  
instructions.)  
460.20502 (5)  
460.20502 (6)  
No  
No  
N/A  
N/A  
None  
Page 28  
460.20503 (1)  
460.20503 (2)  
No  
No  
N/A (See additional  
instructions.)  
Consideration shall be given by  
the operators to maintain this record  
for the duration of the incident  
investigation.  
Consideration shall be given by  
the operators to maintain this record  
for the duration of the incident  
investigation.  
N/A (See additional  
instructions.)  
460.20503 (3)  
460.20504 (1)  
Yes  
No  
5 year minimum  
N/A (See additional  
instructions.)  
None  
Consideration shall be given by  
the operators to maintain the most  
current submission of this record to  
the commission.  
460.20504 (2)  
No  
N/A (See additional  
instructions.)  
Consideration shall be given by  
the operators to maintain the most  
current submission of this record to  
the commission.  
PART 6: ADOPTION OF STANDARDS  
460.20601 (1)  
460.20601 (2)  
460.20602 (a)  
460.20602 (b)  
460.20602 (c)  
460.20602 (d)  
460.20603  
460.20604  
460.20605  
460.20606 (1)  
460.20606 (2)  
No  
No  
No  
No  
No  
No  
No  
No  
No  
No  
No  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
N/A  
None  
None  
None  
None  
None  
None  
None  
None  
None  
None  
None  
History: 1998-2000 AACS; 2019 AACS; 2022 AACS.  
R 460.20502 Construction filings and reports.  
Rule 502. (1) In addition to the requirements contained in 49 C.F.R. § 191.22,  
which is adopted by reference in R 460.20606, an operator or other person proposing to  
construct a gas pipeline or gas pipeline facility shall notify the commission staff not less  
than 60 days before any of the following begins:  
(a) Construction or any planned rehabilitation, replacement, modification, upgrade,  
uprate, or update of a facility, other than a section of line pipe, that costs $1 million or  
more.  
(b) Construction of any of the following gas facilities connected to a transmission  
pipeline system:  
(i) Metering station.  
(ii) Regulating station.  
Page 29  
(iii) Treatment plant.  
(iv) Production plant.  
(v) Compressor unit.  
(c) Construction of a gas transmission pipeline wherein the maximum allowable  
operating pressure will result in a hoop stress of 30% or more of the specified minimum  
yield strength.  
(d) Construction of 1 or more miles of contiguous new or replacement pipeline,  
excluding the length associated with service lines.  
(2) As part of the notification required under subrule (1)(a) to (c) of this rule, an  
operator or other person proposing to construct a gas pipeline or gas pipeline facility shall  
file all of the following before construction begins:  
(a) A facility schematic or map showing the proposed route of the line on a scale  
not less than 3/8 of an inch to 1 mile.  
(b) Engineering specifications covering design, construction, materials, and testing  
and operating pressures.  
(c) Certification that the facilities will be in compliance with these rules.  
(3) As part of the notification required under subrule (1)(d) of these rules, an  
operator or other person proposing to construct a gas pipeline shall comply with the  
requirements in subrule (2) of these rules upon request.  
(4) An application filed under 1929 PA 9, MCL 483.101 to 483.120, 1929 PA 69,  
MCL 460.501 to 460.506, 1923 PA 238, MCL 486.251 to MCL 486.255, or pursuant to a  
commission order meets the requirements of subrules (1) and (2) of this rule.  
(5) Except for distribution facilities, within 60 days following the completion of  
construction and testing of facilities covered by subrules (1), (2), and (3) of this rule, an  
operator shall file a report with the commission containing the information required under  
49 C.F.R. § 192.517, adopted by reference in R 460.20606 of these rules, and R  
460.20314, and a route map of the as-built pipeline.  
(6) If notification under subrule (1) of this rule is not possible due to an emergency,  
an operator shall notify the commission staff as soon as feasible.  
History: 1998-2000 AACS; 2003 AACS; 2010 AACS; 2019 AACS.  
Editor's Note: An obvious error in R 460.20502 was corrected at the request of the promulgating  
agency, pursuant to Section 56 of 1969 PA 306, as amended by 2000 PA 262, MCL 24.256. The rule  
containing the error was published in Michigan Register, 2019 MR 1. The memorandum requesting the  
correction was published in Michigan Register, 2019 MR 1.  
R 460.20503 Reports of incidents; telephonic notice to the commission staff.  
Rule 503. (1) At the earliest practicable moment following discovery, an operator  
shall notify the commission staff of any of the following situations:  
(a) An incident that is reportable pursuant to 49 CFR 191.5, which is adopted by  
reference in R 460.20606.  
(b) An event resulting in estimated property damage of $10,000.00 or more  
including loss to the operator and others, or both, but excluding the cost of gas lost. As  
used in this subdivision, an “event” means on or relating to an operator’s facilities that  
may or may not involve a release of gas.  
Page 30  
(c) An event resulting in the loss of service to more than 100 customers.  
(d) An event involving a customer's gas facility that results in a fatality or an  
explosion causing structural damage.  
(e) An event resulting in an unintentional release of gas estimated by the operator to  
be 1 million cubic feet or more or an unintentional activation of an emergency shutdown  
system of any portion of a compressor station involving a release of gas.  
(f) An event that causes the pressure of any portion of a pipeline system to rise  
above its maximum allowable operating pressure plus the build-up allowed for operation  
of pressure limiting or control devices.  
(g) An event that receives or is likely to receive extensive news coverage or is  
significant in the judgment of the operator, even though it did not meet the criteria of  
subdivision (a), (b), (c), (d), (e) or (f) of this subrule. This subdivision is not subject to the  
penalty provisions of section 11 of 1969 PA 165, MCL 483.161.  
(2) If additional information is received by the operator after the initial report that  
indicates a different cause, more serious injury, or more serious property damage than  
was initially reported, then the operator shall make a supplemental telephone report to the  
commission staff as soon as practicable.  
(3) When requested by the commission staff, an operator shall supplement a report  
made in accordance with subrule (1) of this rule within a reasonable time, with a written  
report giving full details, such as the cause of the incident or occurrence, the extent of  
injuries or damage, and the steps taken, if any, to prevent a recurrence of the incident or  
occurrence.  
History: 1998-2000 AACS; 2014 AACS; 2019 AACS; 2022 AACS.  
R 460.20504 Reports.  
Rule 504. (1) An operator shall concurrently submit a written report that is required  
to be filed with any federal agency by 49 CFR part 191, which is adopted by reference in  
R 460.20606, to the commission at P.O. Box 30221, Lansing, Michigan 48909-0221 or as  
directed by the commission staff.  
(2) An operator required to submit an annual report in accordance with 49 CFR  
191.11 and 49 CFR 191.17, which are adopted by reference in R 460.20606 of these  
rules, shall also submit a supplemental report to the commission staff. In the  
supplemental report, the operator shall subdivide the information in the reports required  
under 49 CFR 191.11 and 49 CFR 191.17 into specific regions identified by the  
commission staff. The staff shall identify and communicate these regions to the operator  
by the end of the calendar year for which the reports are being submitted. As used in this  
rule, “regions” means geographical, operational, or functional areas of the operator’s  
system. These supplemental reports are to be submitted no later than the dates required  
in 49 CFR 191.11 and 49 CFR 191.17 and in a similar format.  
History: 1998-2000 AACS; 2019 AACS; 2022 AACS.  
PART 6. ADOPTION OF STANDARDS  
Page 31  
R 460.20601 Adoption by reference.  
Rule 601. (1) The publications listed in R 460.20603 to R 460.20606 are adopted by  
reference and are a part of these rules, except where they are inconsistent with these  
rules. Publications identified as published by a specific organization are available from  
the organization at the addresses specified in R 460.20602. The public service  
commission also has copies of the publications available for inspection and distribution at  
cost at its offices located 7109 W. Saginaw Hwy., Lansing, Michigan 48917-1120. The  
mailing address is Michigan Public Service Commission, P.O. Box 30221, Lansing,  
Michigan 48909-0221.  
(2) The numbers in parentheses following the publications adopted by reference  
indicate the applicable editions.  
History: 1998-2000 AACS; 2003 AACS; 2019 AACS.  
R 460.20602 Names, addresses, and phone numbers of organizations.  
Rule 602. The names, addresses, and phone numbers of organizations that sponsor  
or publish documents that have been adopted by reference in these rules are as follows:  
(a) American Petroleum Institute (API), 200 Massachusetts Avenue, Washington,  
D.C. 20001-5571, (Phone number: 202-682-8000).  
(b) American Society of Mechanical Engineers (ASME), Two Park Avenue, New  
York, New York 10016-5990, (Phone number: 800-843-2763), or contact its publishing  
division, 22 Law Drive, P.O. Box 2900, Fairfield, New Jersey 07007, (Phone number:  
973-882-1167).  
(c) National Association of Corrosion Engineers International (NACE), 15385 Park  
Ten Place, Houston, Texas 77084, (Phone number: 281-228-6200) or (Phone number:  
800-797-6223).  
(d) U.S. Department of Transportation Pipeline and Hazardous Materials Safety  
Administration (PHMSA), East Building, 2nd Floor, 1200 New Jersey Avenue, SE,  
Washington, D.C. 20590, (Phone number: 202-366-0656) or (Phone number: 800-467-  
4922). To order a standard published in the Code of Federal Regulations (CFR), contact  
the Government Publishing Office, Superintendent of Documents, Attention: New  
Orders, P.O. Box 371954, Pittsburgh, Pennsylvania 15250-7954, (202-512-1803), or visit  
History: 1998-2000 AACS; 2003 AACS; 2009 AACS; 2010 AACS; 2019 AACS; 2022 AACS.  
R 460.20603 American petroleum institute standard; adoption by reference.  
Rule 603. The following American Petroleum Institute standard is adopted by  
reference in these rules and is available at the price listed:  
API standard 1104 titled “Welding of Pipelines and Related Facilities,” (20th edition,  
October 2005, including errata 1 (2007) and errata 2 (2008)), at a cost as of the time of  
adoption of these rules of $304.00. Registered and authorized representatives of  
regulated pipeline operators may also view this edition of API standard 1104 without  
Page 32  
History: 1998-2000 AACS; 2003 AACS; 2009 AACS; 2010 AACS; 2014 AACS; 2019 AACS; 2022  
AACS.  
R 460.20604 American society of mechanical engineers standard; adoption by  
reference.  
Rule 604. The following American society of mechanical engineers standard is  
adopted by reference in these rules and is available at the price listed:  
ASME boiler and pressure vessel code, section IX, titled “Qualification Standard for  
Welding and Brazing Procedures, Welders, Brazers, and Welding and Brazing  
Operators” (2007 edition, July 1, 2007), at a cost as of the time of adoption of these rules  
of $495.00.  
History: 1998-2000 AACS; 2003 AACS; 2009 AACS; 2014 AACS; 2019 AACS.  
R 460.20605 National association of corrosion engineers international standard;  
adoption by reference.  
Rule 605. The following national association of corrosion engineers international  
standard is adopted by reference in these rules and is available at the price listed:  
NACE MR0175/ISO 15156, 2015, titled “Petroleum and natural gas industries –  
Materials for use in H2S-containing environments in oil and gas production” at a cost as  
of the time of adoption of these rules of $255.00.  
History: 1998-2000 AACS; 2003 AACS; 2009 AACS; 2010 AACS; 2014 AACS; 2019 AACS.  
R 460.20606 Pipeline and hazardous materials safety administration standards;  
adoption by reference.  
Rule 606. (1) The following pipeline and hazardous materials safety administration  
standard is adopted by reference in these rules and is available from the U.S. Government  
Publishing Office via the internet at www.ecfr.gov at no charge at the time of adoption of  
these rules and is also available for public inspection from the Michigan Public Service  
Commission, 7109 West Saginaw Highway, Lansing, Michigan 48917: 49 CFR part 40  
entitled “Procedures for Transportation Workplace Drug and Alcohol Testing Programs,”  
(revised October 1, 2023 edition).  
(2)  
The following Office of Pipeline and Hazardous Materials Safety  
Administration  
standards are adopted by reference in these rules and may be ordered from the U.S.  
Government Publishing Office via the internet at www.ecfr.gov at no charge at the time  
of adoption of these rules and are also available for public inspection from the Michigan  
Public  
Service Commission, 7109 West Saginaw Highway, Lansing, Michigan 48917:  
(a) 49 CFR part 191 entitled “Transportation of Natural and Other Gas by  
Pipeline: Annual  
Reports, Incident, and Other Reporting,” (October 1, 2023 edition).  
Page 33  
(b) 49 CFR part 192 entitled “Transportation of Natural and Other Gas by  
Pipeline: Minimum Federal Safety Standards,” (October 1, 2023 edition).  
(c) 49 CFR part 199 entitled “Drug and Alcohol Testing,” (October 1, 2023  
edition).  
History: 1998-2000 AACS; 2001 AACS; 2003 AACS; 2006 AACS; 2009 AACS; 2010 AACS; 2014  
AACS; 2019 AACS; 2022 AACS; 2023 MR 22, Eff. Nov. 30, 2023.  
Page 34  
;