(d) Projects to be constructed in the future to mitigate the loss of natural resources or
environmental degradation.
History: 1993 AACS.
R 281.1308 Project completion explained.
Rule 8. Pursuant to the provisions of section 35(1)(a) of the act, completion of a new,
reconstructed, enlarged, repaired, or altered dam occurs when all the work depicted on all
approved drawings and all specification requirements have been accomplished and all
permit conditions have been implemented before the expiration of a permit.
History: 1993 AACS.
R 281.1309 Inspection schedule.
Rule 9. Inspection reports that are prepared pursuant to the provisions of R 281.1310 are
due on a calendar year basis. The department shall notify the dam owner of the due date,
by certified mail, not later than January 31 of the year in which the inspection report is due.
In establishing an inspection schedule, as authorized pursuant to the provisions of section
37(2) of the act, the department shall compile an alphabetical listing of dams in each hazard
potential classification of high, significant, and low. The inspection schedule shall be
established based on the following provisions:
(a) For high hazard potential dams, every third dam in the alphabetical listing of these
dams shall be inspected each year as follows:
(i) The first, fourth, seventh, tenth, and so on dam in the alphabetical listing will be due
for inspection the first year.
(ii) The second, fifth, eighth, eleventh, and so on dam in the alphabetical listing will be
due for inspection the second year.
(iii) The third, sixth, ninth, twelfth, and so on dam in the alphabetical listing will be due
for inspection the third year.
(iv) The cycle shall be repeated every 3 years.
(b) For significant hazard potential dams, every fourth dam in the alphabetical listing of
these dams shall be inspected each year as follows:
(i) The first, fifth, ninth, thirteenth, and so on dam in the alphabetical listing shall be due
for inspection the first year.
(ii) The second, sixth, tenth, fourteenth, and so on dam in the alphabetical listing shall be
due for inspection the second year.
(iii) The third, seventh, eleventh, fifteenth, and so on dam in the alphabetical listing shall
be due for inspection the third year.
(iv) The fourth, eighth, twelfth, sixteenth, and so on dam in the alphabetical listing shall
be due for inspection the fourth year.
(v) The cycle shall be repeated every 4 years.
(c) For low hazard potential dams, every fifth dam in the alphabetical listing of these dams
shall be inspected each year as follows:
(i) The first, sixth, eleventh, sixteenth, and so on dam in the alphabetical listing shall be
due for inspection the first year.