(D) No state agency or local unit of government that owns, exercises jurisdiction over, or
holds a recorded easement in the area where the earth change will occur has control over
the project during construction. The control prohibited by this subparagraph includes, but
is not limited to, paying for or having a financial interest in the project during construction
or directing contractors and other individuals engaged in construction work. The control
prohibited by this subparagraph does not consist solely of establishing construction
requirements or conducting inspections.
(f) "Nonerosive velocity" means a speed of water movement that is not conducive to the
development of accelerated soil erosion.
(g) "Part 91" means part 91 of 1994 PA 451, MCL 324.9101 to 324.9123.
(h) "Sediment basin" means a naturally occurring or constructed depression used for the
sole purpose of capturing sediment during or after an earth change activity.
(i) "Stabilization" means the establishment of vegetation or the proper placement, grading,
or covering of soil to ensure its resistance to soil erosion, sliding, or other earth movement.
(j) "Storm water retention basin" means an area that is constructed to capture surface water
runoff and that does not discharge directly to a lake or stream through an outlet. Water
leaves the basin by infiltration and evaporation.
(k) "Stream" means a river, creek, or other surface watercourse that may or may not be
serving as a drain as defined in 1956 PA 40, MCLs 280.1 to 280.630, and which has definite
banks, a bed, and visible evidence of the continued flow or continued occurrence of water,
including the connecting waters of the Great Lakes.
(l) "Temporary soil erosion and sedimentation control measures" means interim control
measures that are installed or constructed to control soil erosion and sedimentation and that
are not maintained after project completion.
(m) "Permanent soil erosion and sedimentation control measures" means control
measures that are installed or constructed to control soil erosion and sedimentation and that
are maintained after project completion.
(2) The terms defined in part 91 have the same meanings when used in these rules.
History: 1979 AC; 1998 AACS; 2017 AACS.
R 323.1702 Earth change requirements generally.
Rule 1702. (1) A person shall conduct an earth change in a manner that will effectively
reduce accelerated soil erosion and resulting sedimentation.
(2) A person engaged in an earth change identified in R 323.1704 shall plan, implement,
and maintain acceptable soil erosion and sedimentation control measures in conformance
with part 91, which effectively reduce accelerated soil erosion and off-site sedimentation.
(3) A person shall set forth soil erosion and sedimentation control measures in a plan as
prescribed by R 323.1703. A person shall make the plan available for inspection at all times
at the site of the earth change. The department, or its designated representative, may require
the county or local enforcing agency to file a copy of the plan with the department.
(4) A person shall obtain a permit containing state prescribed information, as required by
R 323.1707, and make the permit available for inspection at the site of the earth change.
History: 1979 AC; 1998 AACS.
Page 2