Exemption from the permit requirements of this code shall not grant authorization for
work to be done in violation of the provisions of this code or other laws or ordinances of
this jurisdiction.
106.4. Permit issuance. The enforcing agency shall review the application, construction
documents, and other data filed by an applicant for a permit in accordance with the act. If
the enforcing agency finds that the proposed work conforms to the requirements of the act,
the code, and all other applicable laws and ordinances, and that all fees prescribed by the
act have been paid, then the enforcing agency shall issue a permit to the applicant.
106.4.3. Expiration. Each permit issued by the code official under the provisions of the
code shall expire by limitation and become null and void if the work authorized by the
permit has not started within 180 days after the date of the permit is issued, or if the work
authorized by the permit is suspended or abandoned at any time after the work has started,
for a period of 180 days. Before work is recommenced on a project where a permit has
expired, the permit must either be restored to “Issued” status and all necessary fees must
be paid, or a new permit must be secured. If the code has changed and the work was not
started, a new permit shall be first obtained, provided no changes have been made or will
be made in the original construction document and that suspension or abandonment has not
exceeded 1 year.
106.4.4. Extensions. A permittee holding an unexpired permit may apply for an extension
of the time within which the permittee may begin work under that permit if for good and
satisfactory reasons. The code official shall extend the time for action by the permittee for
a period not exceeding 180 days if there is reasonable cause. No permit shall be extended
more than once.
107.1 Construction documents.
(1) Construction documents, engineering calculations, diagrams, and other data shall be
submitted in 2 or more sets with each application for a permit. Code officials may require
additional construction documents at any point during construction. The code official shall
require construction documents, computations, and specifications to be prepared and
designed by a registered design professional, licensed in accordance with the occupational
code, 1980 PA 299, MCL 339.101 to 339.2677.
Exceptions:
1. The code official may waive the submission of construction documents, calculations,
or other data if the nature of the work applied for is such that reviewing of construction
documents is not necessary to determine compliance with the code.
2. Construction documents shall not be required when obtaining a permit from the bureau
of construction codes for any of the following circumstances:
a. Alterations and repair work determined by the mechanical official to be of a minor
nature.
b. Business, mercantile, and storage use group buildings having HVAC equipment only,
with 1 fire area and not more than 3,500 square feet.
c. Work completed by a governmental subdivision or state agency costing less than
$15,000.00.
(2) Where special conditions exist, the code official may require additional construction
documents to be prepared by a registered design professional.