prohibited. Controlled load lowering shall be used when the load line standing platform is
used to lower the connector or connectors.
(f) There shall be a communication system between the connector or connectors on a load
line standing platform and the operator of the crane or derrick. The system may be hand
signals or a closed 2-way selective frequency radio system. Hand signals shall be followed
according to appendix A of this part.
(g) An operator of a crane or derrick shall:
(i) Not be authorized to raise or lower the connector or connectors on a load line standing
platform unless the operator is certified by the national commission for the certification of
crane operators or an equivalent crane certification organization.
(ii) Be trained in all of the provisions of R 408.42809(2) before being allowed to transport
the connector or connectors on a load line standing platform.
(h) When a load line standing platform is in use by the connector or connectors, the
operator of a crane or derrick shall maintain the minimum distance from an energized
power transmission or distribution line as required in table 1, as follows:
VOLTAGE
Up to 50 kV
Over 50 kV
MINUMUM CLEARANCE
20 feet
20 feet + 0.8 inch per kV over 50 kV
(i) The load line of a crane or derrick that is used to raise or lower the connector or
connectors on a load line standing platform shall have a safety factor of 10 for the
anticipated load, and be equipped with a swivel to prevent any rotation of the load line
standing platform. A minimum of 1/2-inch diameter load line shall be used.
(j) Neither the load line standing platform nor the boom shall be lowered below the point
where less than 3 full wraps of the wire rope remain on their respective drums.
(k) A crane or derrick that is used to raise or lower a load line standing platform shall be
set level according to the crane or derrick manufacturer's specifications. The travel lock
shall be engaged on a crane when the load line standing platform is in use.
(l) A crane that is equipped with outriggers shall have the beams and jacks fully extended
to provide maximum stability and the floats shall have a stable bearing when the load line
standing platform is in use by the connector or connectors. A crawler crane shall have its
crawlers fully extended when the load line standing platform is in use.
(m) Where a crane or derrick will be used to elevate the connector or connectors on the
load line standing platform to an area where there has been no previous lift of structural
members, a trial lift shall be performed and consist of positioning the load line standing
platform to the position it is to be used with an assumed minimum anticipated load of 1,000
pounds. The operator shall determine that all configurations necessary to reach the work
location will allow the crane or derrick to remain under the 50% limit of the hoisting
capacity; that all systems, controls, and safety devices are activated and functioning
properly; and that interferences do not exist. This will be done at each set-up location of a
crane or derrick prior to elevating the connector or connectors.