(b) The reclamation problems involved.
(c) The operator's plan of action to prevent erosion and pollution, to attain revegetation,
and to achieve the ultimate reclamation of the mining area in accordance with the purposes
and requirements of the act and the rules adopted thereunder.
(d) An estimate time schedule for completion of the plan, and the proposed purpose for
which the land is to be used upon completion.
(e) Estimated cost of reclamation.
(f) Other pertinent information that the supervisor may deem necessary.
(4) If circumstances warrant, or if development of an environment plan is dependent upon
unknown factors which cannot or will not be determined except during the progress of the
operation, a partial plan may be submitted and supplemented as new plans are developed.
(5) If the surface landowner and the operator are 2 separate persons, the surface landowner
shall be given an opportunity to comment on the operator's environment plan before the
operator submits the plan to the supervisor.
History: 1979 AC.
R 425.9 Evaluation of environment plan.
Rule 9. (1) Upon receipt of an environment plan, the supervisor shall evaluate it in terms
of the reclamation required by the act. The supervisor may consult with and obtain
assistance of other divisions of the department in the evaluation process. The supervisor
may reject a plan or any part thereof, and shall give reasons in writing, together with
recommendations for modification of a plan to meet his objections, if the reclamation
specified by a plan does not conform to the requirements of the act and these rules, or if,
in the opinion of the supervisor, it is not feasible or is otherwise undesirable because of the
following:
(a) Erosion is likely to occur in the sloping, terracing, or other treatment of stockpiles and
tailings basins, which may result in injury or damage to fish and wildlife or the pollution
of public waters or which may cause injury to the property or person of others.
(b) Vegetation or other practical treatment of tailings basins and stockpiles, upon
becoming permanently inactive, is not satisfactory.
(c) The surface overburden banks of open pits in rock, and the entire bank of open pits in
unconsolidated materials, upon their abandonment will not be stabilized.
(d) The cleanup of plantsite and mining areas, and the removal of debris therefrom on
termination of the mining operation, will not be satisfactory.
(2) If the supervisor rejects an environment plan, an operator may resubmit the plan as
revised so as to meet the supervisor's objections.
(3) If an environment plan is satisfactory, the supervisor shall approve it and promptly
notify the operator by written statement that compliance with the plan by the operator
fulfills the requirements of the act with respect to the mining area or any portion thereof
involved. The approval of an environment plan for a long-lived mining operation may be
conditioned on periodic review in light of new research and changed reclamation
technology. An approved environment plan shall be referred to as the reclamation plan.
(4) A reclamation plan may be modified at any time by mutual consent of the supervisor
and operator to adjust to changed conditions or technology, or to correct an oversight.
(5) The supervisor may modify the reclamation plan when:
Page 4