(vii) Storage, relocation, and disposal of overburden, waste rock, ore, and tailings within
a mining area, including backfilling of mined areas.
(viii) Storage and transportation of chemical reagents.
(ix) Construction of water impoundment and drainage features.
(x) Construction of haul roads.
(xi) Construction of utilities or extension of existing utilities.
(xii) Withdrawal, transportation, and discharge of water.
(b) "Nonerosive velocity" means a speed of water movement that is not conducive to the
development of accelerated soil erosion.
(c) "Organization report" means a certified statement, on a form prescribed by the
department, giving the name, address, and plan of the business organization, and listing the
following:
(i) All corporate officers, directors, incorporators, and limited liability company
managers.
(ii) All other partners, shareholders, limited liability company members, or other persons
who have the authority to make, or are responsible for making, operational decisions,
including the construction, operation, closure, postclosure monitoring, reclamation, and
remediation of a mine.
(d) "Overburden" means unconsolidated earth material that overlies bedrock and that is
or will be excavated by open pit mining methods to access ore.
(e) "Percolation leaching" means a process for the primary purpose of the recovery of
metals in an outdoor environment from a stockpile of crushed or excavated ore by
percolating water or a solution through the ore and collecting the leachate, and includes the
processes known as "heap leaching" and "dump leaching."
(f) "Peripheral rock" means rock that is or will be left in place after the completion of
mining and within 3 feet of either of the following:
(i) The walls and floor of an open pit.
(ii) The walls, floor, and roof of adits, portals, and underground mine workings.
(g) "Permanent soil erosion and sedimentation control measures" means control measures
that are installed or constructed to control soil erosion and sedimentation and that are
designed to remain in place after final reclamation.
(h) "Postclosure" means the period following completion of final reclamation in
compliance with the approved reclamation plan.
(i) "Public water supply well" means a well that provides water for a "type I public water
supply," "type IIa public water supply," "type IIb public water supply," or "type III public
water supply" as those terms are defined in R 325.10502.
(j) "Reactive" means susceptible to reacting, dissolving, or otherwise forming a leachate
that is or may be harmful to the environment or to human health and safety as determined
by the department under conditions that exist, or may exist, at a mining operation.
(k) "Reclamation" means that reconditioning or rehabilitation of the mining area or
portions thereof for useful purposes and the protection of the natural resources, including
the control of erosion and the prevention of land or rock slides, collapses and subsidence,
and air and water pollution.
(l) "Remediation" means the taking of actions that are necessary to prevent, minimize, or
mitigate injury to the public health, safety, or welfare, or to the environment, including
cleanup, removal, containment, isolation, destruction, or treatment of a hazardous
Page 4