Agency Report to JCAR-Page 2
Section 173 of Public Act 295 of 2008, MCL 460.1173(1) (Act 295), authorized the Commission to
promulgate administrative rules governing net metering standards. In 2009, the Commission
formally adopted administrative rules governing electric interconnection and net metering. See, Mich
Admin Code, R 460.601a-460.656. Those rules focused primarily on small electric generators by
dividing them into five categories; the first four categories apply to projects up to 2 megawatts
(MWs) and the fifth category applies to projects greater than 2 MWs. In the December 20, 2012
order in Case No. U-15919, the Commission adopted procedures for interconnection of smaller
projects (Categories 1 and 2), but has not yet adopted procedures governing the interconnection of
larger projects (Categories 3 through 5). Those net metering rules are now outdated and need to be
rescinded. A separate RFR has been submitted for that.
There have been significant changes in Michigan’s energy landscape driven by rapidly advancing
renewable energy technology, including solar, wind, and battery storage. There have also been
changes in Michigan’s energy laws with the passage of Public Acts 341 and 342 of 2016, which,
among other things, amended Act 295. MCL 460.1173(1) now authorizes the Commission to
promulgate rules governing distributed generation (DG). See also, MCL 460.1173(6)(b). Likewise,
the Institute of Electrical and Electronics Engineers (IEEE) recently updated its technical standards
for interconnection, the IEEE Standard for Interconnection and Interoperability of Distributed Energy
Resources with Associated Electric Power Systems Interfaces (IEEE 1547-2018), which has
prompted other states to revise their own interconnection rules and standards. Moreover, the Federal
Energy Regulatory Commission (FERC) has recently addressed the integration of energy storage
facilities in its Order 841 issued on February 15, 2018, which directs regional transmission
organizations and independent system operators to establish market rules for energy storage facilities
to participate in wholesale energy, capacity, and ancillary services markets. Order 841, 162 FERC ¶
61, 127; 18 CFR 35.28 (2018).
Finally, in the October 27, 2015 order in Case No. U-17973, the Commission determined that it
needed to update the standards applicable to utilities and qualifying facilities (QF) operating pursuant
to the Public Utility Regulatory Policies Act of 1978, 16 USC 2601 et seq., 16 USC 824a-3
(PURPA). PURPA was enacted by Congress in 1978 to increase energy conservation and energy
efficiency by allowing for renewable resources to interconnect with and sell their generation to
utilities. PURPA is largely carried out by the states. 16 USC 2621(b)(2); 16 USC 824a-3(f). For
example, the rates paid to QFs are set by the Commission. 16 USC 824a-3; MCL 460.6j(13)(b).
Thus, both PURPA and the new DG law (as well as the legacy net metering law) concern the topic of
interconnection with the energy grid. Industry standards for interconnection have been updated since
the 2009. The Commission’s current rules are outdated and need to be replaced. The Commission
expects that the new rules will decrease the time required to interconnect a distributed energy project
into the electric distribution system. Larger generators tend to be interconnecting with the utility
under PURPA requirements. In this rulemaking, the Commission will promulgate new rules
addressing interconnection requirements for generators of all sizes, DG standards, and legacy net
metering, to address the concerns described herein. Simultaneously, the Commission is rescinding
the 2009 interconnection and net metering rules.
This proposed ruleset was previously included in 2019-087, which was voided on March 10, 2020.
MCL 24.242 and 24.245